Denounce the abandonment and non commissioning since its construction in 2009 of the Deposit of Drinking Water in Las Viņas-Carivete

Source:

The aldermen of IU-green raise a motion in Parliament for the immediate implementation of this Infrastructure

It has a capacity of 500 cubic meters and cost the pockets of Murcia whopping 909,000 euros

Another sign of the apathy of the Popular Party in Totana is the status of Drinking Water Reservoir, built in 2009 which should cater to the residents of the hamlet of Las Viņas and Carivete.

A work, funded by the Autonomous Community, which had a cost of more than 909,000 euros and is practically useless, while the neighbors do not have this basic service with normality to which they are entitled, according to reports from IU-green in a statement.

A deposit of 500 cubic meters capacity built and drive that would be supplied from Network Virgen de las Huertas also encounters many problems in summer by the lack of planning investments in the root problem of the government team Popular Party.

As happened with the Deposit of Sierra, which was "given" by the PP to Urbanization of the term of Aledo, sometimes the council of the PP in Totana not seem to know what to do with water infrastructures that have cost hundreds of thousands of million and must meet the Public Service between citizens of Totana for which they were designed, not letting it deteriorate for its abandonment.

From Green IU, was harshly criticized this situation of neglect in management and calls for a solution in the area for which they have raised a proposal to the regular plenary session of November, asking Commonwealth Taibilla Channel, an allocation of water the area through the Facilities and Drive Aledo, located in the municipality of Totana (Highway de la Huerta), connecting with Cot deposits and Virgen de las Huertas would increase the capacity and resources, ensuring the supply in decades and abandoned, unused in the hamlet of Las Viņas and launching Carivete deposit.

"We believe the millionaire debt of the City of Totana with MCT, could be an incentive, but in our proposal a considerable saving in energy costs could face a Payment Plan and amortization of works in a few years is contemplated ... "said Juan Jose Canovas, spokesman and Councilman Green IU in Totana.

noticia
Denounce the abandonment and non commissioning since its construction in 2009 of the Deposit of Drinking Water in Las Viņas-Carivete, Foto 1
Denounce the abandonment and non commissioning since its construction in 2009 of the Deposit of Drinking Water in Las Viņas-Carivete, Foto 2
Denounce the abandonment and non commissioning since its construction in 2009 of the Deposit of Drinking Water in Las Viņas-Carivete, Foto 3
Denounce the abandonment and non commissioning since its construction in 2009 of the Deposit of Drinking Water in Las Viņas-Carivete, Foto 4

Comment this news on Facebook

If you want to comment on this news to the administrators of Totana.net, fill out the form below:

Send notification Code: 2024419
The owner of the personal data, collected in this form, expressly authorizes Alamo Networks, S.L. to treat said data in a computerized way and to be able to incorporate it into your database. The user may exercise the rights of access, rectification, cancellation and opposition of their personal data, in the terms established by the LOPD, at the address set in C / Alamo 8, 30850, Totana (Murcia). For your convenience you can also exercise your rights by email at the address info@totana.net
This website uses cookies to facilitate and improve navigation. If you continue browsing, we consider that you accept its use. More information