Win Totana: The City Council receives a new ruling from the Supreme Court in which it is ordered to pay € 6,759,360 "for two disastrous actions of the PP in 2009 and 2012"

Source:

"This goes to corroborate the manifest irresponsibility that already in its day was denounced by this group when in 2009 approves expansion of water service contract with the vote of the 13 popular councilors, among which were Isabel María Sánchez and the current mayoral candidate, Juan Pagán "

New economic blow for the City of Totana with a ruling dated February 15, 2019 in which the Supreme Court ordered us to pay € 6,759,360 plus costs to the company Socamex and Urbaser for rescission of contract with it in September 2012. Legal services are currently studying whether to appeal to the Supreme Court, although this ruling is the result of an appeal by both parties where justice again gives the reason to the complainant company.

"This corroborates the manifest irresponsibility that was already denounced by this group when, in 2009, the Popular Party approved the extension of the contract for Socamex and Urbaser with the vote of its 13 councilors, among whom They found Isabel María Sánchez and the current mayoral candidate for the PP, Juan Pagán.

An agreement by which the water service was delivered and shielded to the aforementioned company until 2032, with leonine and unbearable conditions for the municipality and for the neighbors, increasing year after year the payments for the service, going from assuming a cost of € 3,655,000 in 2009 to € 15,126,000 in 2032. "They claim from winning Totana.

This agreement was also accompanied by an injection of liquidity that the city needed desperately, so that 6,000,000 were deposited in the municipal coffers as an agreement shield.

Of which more than half disappeared before arriving, as they were used to settle the debt with the company of waste collection of this same concessionaire.

In addition, the company was allowed to withhold revenues from neighbors' receipts to ensure their collections and benefits.

All this allowed and agreed by the Popular Party in 2009.

In 2012, the then Mayor, and current spokesperson of the PP realizes that what she and her colleagues voted irresponsibly in 2009 is something that the city can not assume due to the leonine conditions that approved and the contract is terminated, so that the company claims the City Council for breach and obtains the reason for justice twice.

How did the Popular Party think that it would maintain a service and a sanitation in payments to the company of RSU and Taibilla?

In fact, both entities were blocked and the debt reached the known levels.

"This is just a sample of the disastrous management of the Popular Party and we demand that the political responsibilities of the people involved be assumed and that they explain to the people of Totana how their actions translate into millionaire debts that we now have to pay among all and add a new slab to the serious economic situation that we suffer for this and other efforts and waste of the government of the PP of Andreo and Juan Pagan.

So we reiterate the proposal to hold discussions among the heads of the list to analyze this and other issues of vital importance in the municipality for which a solution must be proposed. "The formation of the left concludes.

noticia
Win Totana: The City Council receives a new ruling from the Supreme Court in which it is ordered to pay € 6,759,360 "for two disastrous actions of the PP in 2009 and 2012", Foto 1
Win Totana: The City Council receives a new ruling from the Supreme Court in which it is ordered to pay € 6,759,360 "for two disastrous actions of the PP in 2009 and 2012", Foto 2

Comment this news on Facebook

If you want to comment on this news to the administrators of Totana.net, fill out the form below:

Send notification Code: 2024419
The owner of the personal data, collected in this form, expressly authorizes Alamo Networks, S.L. to treat said data in a computerized way and to be able to incorporate it into your database. The user may exercise the rights of access, rectification, cancellation and opposition of their personal data, in the terms established by the LOPD, at the address set in C / Alamo 8, 30850, Totana (Murcia). For your convenience you can also exercise your rights by email at the address info@totana.net
This website uses cookies to facilitate and improve navigation. If you continue browsing, we consider that you accept its use. More information